Reliability Backstop Procurement

One-time capacity procurement auction designed to secure new power supply resources for data centers and large loads, with 15-year contracts and $555/MWday price cap.

News volume 3 stories in 90 days
23 Aug: 0 stories24 Aug: 0 stories25 Aug: 0 stories26 Aug: 0 stories27 Aug: 0 stories28 Aug: 0 stories29 Aug: 0 stories30 Aug: 0 stories31 Aug: 0 stories1 Sep: 0 stories2 Sep: 0 stories3 Sep: 0 stories4 Sep: 0 stories5 Sep: 0 stories6 Sep: 0 stories7 Sep: 0 stories8 Sep: 0 stories9 Sep: 0 stories10 Sep: 0 stories11 Sep: 0 stories12 Sep: 0 stories13 Sep: 0 stories14 Sep: 0 stories15 Sep: 0 stories16 Sep: 0 stories17 Sep: 0 stories18 Sep: 0 stories19 Sep: 0 stories20 Sep: 0 stories21 Sep: 0 stories22 Sep: 0 stories23 Sep: 0 stories24 Sep: 0 stories25 Sep: 0 stories26 Sep: 0 stories27 Sep: 0 stories28 Sep: 0 stories29 Sep: 0 stories30 Sep: 1 story1 Oct: 0 stories2 Oct: 0 stories3 Oct: 0 stories4 Oct: 0 stories5 Oct: 0 stories6 Oct: 0 stories7 Oct: 0 stories8 Oct: 1 story9 Oct: 0 stories10 Oct: 0 stories11 Oct: 0 stories12 Oct: 0 stories13 Oct: 0 stories14 Oct: 0 stories15 Oct: 0 stories16 Oct: 0 stories17 Oct: 0 stories18 Oct: 0 stories19 Oct: 0 stories20 Oct: 0 stories21 Oct: 0 stories22 Oct: 0 stories23 Oct: 0 stories24 Oct: 0 stories25 Oct: 0 stories26 Oct: 0 stories27 Oct: 0 stories28 Oct: 0 stories29 Oct: 0 stories30 Oct: 0 stories31 Oct: 0 stories1 Nov: 0 stories2 Nov: 0 stories3 Nov: 1 story4 Nov: 0 stories5 Nov: 0 stories6 Nov: 0 stories7 Nov: 0 stories8 Nov: 0 stories9 Nov: 0 stories10 Nov: 0 stories11 Nov: 0 stories12 Nov: 0 stories13 Nov: 0 stories14 Nov: 0 stories15 Nov: 0 stories16 Nov: 0 stories17 Nov: 0 stories18 Nov: 0 stories19 Nov: 0 stories20 Nov: 0 stories
Snapshot
Domain
electricity capacity procurement 1 source
Prime contractor
PJM 1 source
Cost
$555 per megawatt-day price cap 1 source
Status
development 1 source
Intelligence coverage

Reliability Backstop Procurement is a one-time capacity procurement auction mechanism designed to secure new power supply resources for data centers and large industrial loads within the PJM electricity market.

Structure and Terms

The programme operates through a competitive auction format with 15-year contracts for capacity resources 1. Pricing is capped at $555 per megawatt-day 1, establishing a ceiling on procurement costs.

Scale and Cost

The programme carries billion-dollar implications for consumers 2, with total programme costs estimated at approximately $20 billion 3.

Governance and Participants

PJM serves as the primary administrator of the programme 4. The Federal Energy Regulatory Commission maintains regulatory oversight 3.

Participating utilities and operators include 4:

  • PPL Electric (confidence medium)
  • AES Ohio (confidence medium)
  • FirstEnergy (confidence medium)

Purpose

The backstop procurement mechanism addresses capacity needs within the PJM region's electricity grid, targeting resources required to meet demand from data centers and other large loads. The fixed contract term and price cap structure provide cost predictability while incentivizing new capacity development.

Facts 4

AttributeValueConfidenceSourcesCited
Domain electricity capacity procurement
also reported: electricity grid capacity procurement (low), energy (low)
low 1 1
Prime contractor PJM low 1 4
Cost $555 per megawatt-day price cap
also reported: 20000000000 (low), billion-dollar implications for consumers (low)
low 1 1
Status development low 1 5

Participants 5

FirstEnergyPPL ElectricAES OhioPJMFERC

Frequently mentioned together 5

Sources 5

  1. PJM’s old way of getting power built isn’t working. Has it found a fix? · Canary Media
  2. FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction · Utility Dive
  3. PJM files backstop auction plan at FERC to meet capacity shortfall · Utility Dive
  4. PJM’s revised data center backstop procurement plan reduces utility risks: ICF · Utility Dive
  5. DOE presses PJM on ratepayer protections from large load costs · Utility Dive
That's Frontier for today

Tomorrow's desk, in your inbox by 06:00 UTC. The week's best stories, every Sunday. The month that mattered, on the 1st.

Drawn from the 519 sources the paper read this month. Text and HTML, one-click unsubscribe, free.

How often
Your desks