Tentative schedule for MTC-T calls for six systems within 18 months of award
For its Mobile Tactical Cannon-Tracked competition, the Army is asking vendors to submit a "notional delivery schedule" showing they can deliver three MTC-T systems within 12 months of receiving an award and an additional three within 18 months. The service released a call for solutions for the MTC-T effort on Nov. 2 in its ongoing effort to replace the M109 howitzer, with responses due Nov. 16. A Nov. 5 amendment to the notice adds the tentative delivery schedule. "Offerors shall also describe the assumptions, production conditions, integration activities, test events and key risks affecting schedule achievability," the amendment states. A "tentative" test schedule breakdown from the Army
…