Unproductive hours on submarine contract more than halve
The prime contractor on a nuclear submarine contract recorded almost forty thousand unproductive hours in 2025-26, down from more than ninety four thousand the year before, with the losses arising where government furnished assets were not available to the supply chain when required, according to answers given in Parliament. Ben Obese-Jecty, the Conservative member for Huntingdon, asked how many unproductive hours there were and, in a second question, for what reason those hours were unproductive, following an answer given on 23 September. Luke Pollard, the Minister of State for Defence, gave the same answer to both: “The Prime Contractor recorded 39,872 unproductive hours in 2025-26, a
…