Marham runway repairs done three weeks ahead of plan
Resurfacing work at RAF Marham has been completed in five weeks against an eight-week programme, and Lightning Force operations ran from a taxiway while all three runways were out of use, according to the Defence Infrastructure Organisation. The £3.5 million project covered 28,000 square metres of the runway intersection, last resurfaced in 2018, and dealt with deterioration below the surface as well, with just over 4,000 square metres of underlying pavement needing repair before the new surface could go down. A further 675 square metres was resurfaced on Runway 05. Because the work sat at the intersection, every runway was unavailable at once. Contractor movements were coordinated with air
…