How did you sequence a phased SASE deployment?
Just about to start moving off our old hub and spoke VPN to SASE and im not doing it big bang, that feels like a great way to take the whole company down on a Monday. Phasing it instead. Rough plan is cloud SWG first and split the internal traffic back to the existing VPN, get remote users off the legacy client early since thats where the pain is and leave the site tunnels and full TLS inspection for later once the easy wins are in. For those whove done a phased SASE rollout, am interested to hear what you’d leave out of phase one. submitted by /u/kevinelevent [link] [comments]