The Navy’s shipyard upgrades could take 50 years, cost $200 billion

The Navy’s plan to modernize and upgrade its four shipyards in the coming years could take half a century and cost more than $200 billion, a new report found. The Government Accountability Office released a new report on the Navy’s Shipyard Infrastructure Optimization Program (SIOP) on Friday. The report, “Naval Shipyards: Complete Information Needed for Decision-Making on Multibillion-Dollar, 50-Year Infrastructure Program,” found that the price tag has noticeably grown since it started, and that the effort lacks plans for regular reviews of its progress. That lack of oversight and evaluations risks further cost increases and new challenges. “However, the Navy has not outlined steps in the
…