‘Risking billions’: US Navy’s massive shipyard overhaul lacks oversight, watchdog says

The U.S. Navy’s Shipyard Infrastructure Optimization Program will exceed $200 billion and take more than 50 years to execute, but the program is not regularly evaluated for its costs, risks and performance, according to a new Government Accountability Office report.The lack of oversight could lead to Congress making consequential decisions “based on incomplete information, thus risking billions in taxpayer dollars,” the GAO wrote in its report, published Friday.The findings come as the Navy undertakes a generational effort to improve poor conditions and outdated infrastructure at the shipyards in Norfolk, Virginia; Pearl Harbor, Hawaii; Portsmouth Naval Shipyard in Kittery, Maine; and Puget
…