The US Army wants nuclear microreactors on bases by late 2028, but Qs about the plan still linger.
Transcript
Machine-transcribed by YouTube. Expect errors in names, commands and version numbers.
The White House has tapped the Army with leading the charge on developing these dualuse small micro reactors. The service recently moved out with the Janis program, tapping five companies and awarding them a grand total of $2.2 billion collectively to develop, field, and test 20 of these reactors. The first one should be operational on a US base within fall 2028. Jeff Wexman, the principal deputy assistant secretary of the army for installations, energy, and environment, recently walked reporters through a host of questions he, other service officials, and the government at large are trying to sort through. One of the first questions that the Army is grappling with is what to do with the nuclear waste. All companies have been giving a mandate that they must get all their waste and no contamination could be left behind within two years of their micro reactors going offline.