Twin Icebreaker Projects Progressing at Bollinger’s Gulf Coast Yards

Modules of the future Polar Security Cutter under construction at Bollinger Mississippi on Aug. 5, 2026. USNI News PASCAGOULA, MISS. — The rose-brown hull of the first heavy polar icebreaker for the Coast Guard is taking shape after years of delays on the Gulf Coast. The stern sections of the future USCGC Polar Sentinel (WMSP-21) are now standing almost four stories high in the middle of the Bollinger Mississippi shipyard, USNI News observed during a visit to the shipyard on Aug. 5. As of early August, the stern section of the future Polar Security Cutter was positioned to be welded in place. A few hundred yards away, workers in the steel panel line of the shipyard were working in the
…