Report: VC-25B delays caused by lingering issues with interior modifications
Ongoing delays facing the VC-25B Air Force One replacement program can be traced back to a 2023 shift to a new interior design manufacturer, according to a report recently released by the service. “The primary driver for this program's multiple schedule breaches continues to be design instabilities stemming from the transition to a new interiors supplier. Boeing finalized the transition to a new subcontractor in December 2023, but the design maturity for the aircraft interior continues to lag due to numerous technical and certification issues,” the Pentagon wrote in its Modernized Selected Acquisition Report, released on Aug. 3 but dated April 21. “Boeing's slow design progress on the
…