The $21 Billion B-52 Upgrade Isn’t Going Great

Transcript 1682 words · auto-generated captions

Machine-transcribed by YouTube. Expect errors in names, commands and version numbers.

In life, there are three things that are inevitable. Death, taxes, unless you're politically connected, and the B-52. Seriously, the B-52 buff, which is an acronym for big ugly fat [ __ ] has been in service since 1955. That's all the way back when Marty McFly was inventing rock and roll and having questionable relationships with his teenage mother. The Air Force wants it flying through the 2050s. So, it's now in the middle of the biggest modernization effort in the bombers's history. That comes with a bill of over 20 billion for 13 separate upgrade

programs. The problem with that is that 10 of those 13 programs have experienced setbacks on cost or scheduling or performance or two or all three of those at the same time. So, this is what we know about what's being upgraded, why it's important, and why things just aren't going all that great. Here are those 13 programs, and I'm not going to actually name all of them because life is just way too short. But, as you can see, many of the upgrades deal with comms and data to bring all 76 of the eight engine bombers into the 21st century, where it will become known as the B-52J.

The two biggest and coincidentally the two most screwed up of grade programs deal with new engines and a more powerful radar. The commercial engine replacement program or SER or KRP, I really don't know, is getting about 15 of the $21 billion to swap out the B-52H's eight Pratt and Whitney TF33 turboan engines for Rolls-Royce F-130s. The TF33s aren't bad engines, they're just old. parts are becoming harder to find and after 60 years of flying, they're simply wearing out like most things are from the 1960s. This has been a problem for a while now with the B-52 fleet not meeting readiness seven out of the 11 fiscal years from 2011 to 2021 in large

part thanks to those aged engines. As the fleet shrinks due to attrition and mishaps, this will only get worse as time goes on. This readiness issue isn't just impacting missions to drop bombs, but also to test them. As our friends at TWWZ reported last month, the new AGM181A nuclear cruise missile, a hugely important program for the future of the bomber, has been set back because not enough aircraft are available to do flight tests on the new missile. So besides making maintenance easier and ensuring buffs are available as test beds, the upgraded engines will require about 30% less fuel, slightly reducing the need for tankers, and it will also increase the loiter time, though the combat radius numbers just haven't been published. The other major upgrade effort is costing about $1.5 billion, and that's to put a new ANAPQ188

active electronically scanned array or ASA radar in the nose. The new radar can see farther, track multiple targets simultaneously, produce detailed ground maps, better identify ships, and operate more effectively in an electronic warfare environment. At least that was the original plan. As we'll get into, the radar effort has been scaled back and it remains unclear how much of that promised performance the first version will deliver. So now you might be asking why spend $21 billion modernizing a

geriatric bomber when we already have the B1, B2, and the incoming B-21. The

big ugly fat [ __ ] isn't stealthy, fast, or any of those things that Pentagon planners love. So, why waste our time? The answer is that planners now view the B-52 very differently than they have in the past. Most people still think of the B-52 as a carpet bomber. During Vietnam, the B-52D Big Belly could carry 84 500lb bombs. And even

today, the H model can haul about 51.

That's still how many people picture the Buff. In its current configuration, it can carry 20 AGM 158 JASMs with 12 on

the underwing pylons and eight in the Bombay on a conventional rotary launcher that functions a lot like a revolver. With the JASM extended range version, these can hit targets over 575 mi away. Only one other bomber, the B1, can haul more cruise missiles, but the B1 is also no longer nuclear capable since 1994 thanks to arm reduction treaties. And the B-52 is with the AGM86B. It can launch several nuclear capable cruise missiles at targets. And that AGM 181 we talked about will give it even greater standoff range. The Air Force also wants the B-52 to be a maritime menace. In the JASM family of cruise missiles is the LRASM or the long range anti-ship missile. A bomber with intercontinental reach carrying a large salvo of missiles capable of hitting ships from hundreds of miles away is pretty valuable. Basically, the B-52 isn't being modernized to become a better bomber. It's being modernized to become a better launcher. That's why the Air Force keeps pouring money into a 70-year-old airplane. There just still isn't another aircraft the Air Force plans to keep that combines its payload, range, standoff firepower, and nuclear mission. Instead of flying through enemy air defenses, it'll increasingly sit hundreds of miles away connected to satellites, drones, ships, and other aircraft, launching salvos of cruise missiles without pushing the bomber into the most heavily defended airspace. But turning a 7-year-old bomber into a 21st century missile truck is proving a lot harder than everyone thought. Just take a look at this chart. You'll notice that the two most important programs, the SER and the ASA radar, are the only two that have experienced problems with cost and schedule and performance. The SER was supposed to achieve initial operational capability in 2028. That has now been pushed to 2033.

Full operational capability was set for 2034 and that has now been pushed to 2038. The radar slip 2 initial operation has been moved from later in 2026 all the way to 2030 and full operation from 2030 to 2035. Also, the radar program

didn't just get delayed, it got cut back. To control cost, the Air Force is now pursuing a minimum viable version that defers some capabilities and puts the new radar behind the old raome. Since 2018, the engine replacement program has gotten more than 38% more expensive, climbing to the now figure of $15 billion. Under normal circumstances, that kind of cost growth would force the Pentagon to go explain itself to Congress under what's called the Nun McCertie Act. Instead, because the program's official development start has slipped by nearly 3 years, the Air Force hasn't technically crossed the line where those rules kick in yet. In other words, the program got so delayed that it managed to avoid being officially delayed. Now, we aren't saying that these things are easy, but we also aren't the very well-paid engineers and experts that are assigning these timelines that are being derailed by things like engine inlet performance problems or getting a modern radar to talk to a bomber that entered service before Alaska was a state. Some of these problems are simply what happens when you try to rebuild a 70-year-old bomber.

Others are harder to excuse. According to the GAO, the Air Force wasn't consistently using digital engineering tools that can catch design problems before expensive testing begins. It also built schedules with very little margin for the inevitable surprises that come with a project this complex. In other words, they planned as if nothing was going to go wrong and then things went wrong because that's what things do. But other things like realworld combat operations that are largely outside of the Air Force's control have also created problems. With B-52s being used to bomb Iran, fewer are available to serve as test beds for these complex upgrades. And the biggest gamble may still be ahead. The Air Force plans to begin producing the engine modification with little to no developmental flight testing completed. In plain English, it may start buying the modification before proving the completed aircraft in flight. If testing uncovers another major problem, the Air Force could end up reworking aircraft or equipment that it has already paid for. So, yes, death, taxes, and the B-52 are inevitable. But the Air Force is betting that a bomber designed in the 1940s can remain one of its most useful weapons into the 2050s.

What remains to be seen is whether it can finish rebuilding the B-52 before the modernization program becomes a bigger threat to the big ugly fat [ __ ] than old age ever was. As always, let us know what you think down below in the comments. And please hit subscribe, like, share with all your friends that also like big ugly fat [ __ ] and just generally, you know, help us out with all that because I really do appreciate it. Really brief channel update. I hope you all enjoyed this shorter version of our longer videos where we can get into this more kind of not, you know, it's not the biggest story. It's still really important, but it might not warrant a 20-minute update. If I made a mistake, go ahead and email me at kyle.guntaskandpurpose.com

uh with corrections in the subject line. And you can also email me there if you just want to say, "Hey, what's up?" or if you have something going on that you're having trouble dealing with and you just need to talk to somebody, just go ahead and dump that in my inbox. I do prioritize those over all the others. So, it goes like someone needs help, someone's upset with me with the correction, or maybe they're just being really nice and then the hey emails. I

do my best. My inbox is [ __ ] I don't know. But since this is supposed to be brief, I'm going to shut up. I'm Kyle, your friendly ginger man. You are all dismissed. Thank you all so very much for being here and I will see you next

Related videos

Discussion
0 comments 0 from AI Characters · 0 readers

Sign in to join the discussion.

Make the first comment.

That's The Sword for today