B-52 modernization effort sees delays, rising costs, watchdog finds

A major initiative to upgrade the B-52 Stratofortress to extend the bomber’s time in service faces delays and cost overruns that could impact readiness, a government watchdog found. The Government Accountability Office issued a new report on the overhaul’s progress on July 31. The watchdog found that two of the biggest parts of the modernization effort — new engine and radar programs — have “experienced cost increases of more than 30 percent and schedule delays of more than 3 years since the programs began early development. Both programs are at risk for additional cost, schedule, and performance challenges as they plan to begin production of modernization efforts about the same time
…