Saudi MMSC Vessels Face Additional Design Fixes and Delays

Published in June, a new contract stipulated the need for additional design and engineering work for all 4 Multi-Mission Surface Combatants (MMSCs) for the Royal Saudi Navy (RSN). In particular, deficiencies with trial cards used to document issues with the ship along with newly identified discrepancies resulted in the need for additional work. The additional design work will also resolve previously approved engineering changes/work left unfinished before each of the vessels deliveries. This work will affect all 4 MMSCs destined for the RSN, including the already launched HMS Saud (820), which hit the water at Fincanteri’s Marinette, Wisconsin shipyard in December of 2025 (with Naval News
…